Beginning Wednesday, May 1, Perfection Painting Corp. will commence the Civic Center Painting Project, anticipated to conclude by Friday, May 31.

This project will focus on maintaining and enhancing the exterior surfaces of the City Hall, Community Center, and the Parking Structure. To achieve this, the Contractor will undertake a comprehensive approach involving painting exterior surfaces and necessary repairs to prepare these facilities for a fresh coat of paint.

 

Schedule Details

Project Timeline: May 1, 2024 - May 31, 2024

  • City Hall and Community Center Painting: Monday through Friday, 8:00 a.m. to 4:30 p.m.
  • Parking Structure Painting: Overnight, 6:00 p.m. to 2:30 a.m.

To minimize inconvenience and ensure uninterrupted access to the Parking Structure during business hours, the Contractor will execute the painting overnight, floor by floor. "No Parking" signs will be prominently displayed before work commences.

Civic Center Painting Project

Civic Center Painting Project Timeline

Project Execution

Efficient execution of the project requires simultaneous work across various areas, including weekends and evenings. Consequently, portions of sidewalks, pathways, and building perimeters will be temporarily blocked off to facilitate the necessary work. Access to entrances will be maintained throughout, with clear detours and flagmen to guide pedestrians safely around the work areas.

 

Special Event Consideration

The project schedule has been meticulously planned to minimize disruptions to important community events such as Farmer’s Market, Downtown Events, local High School Prom, and Concerts in the Park.

  • Notice for 5/11 - 5/31 : Painting of City Parking Structure is scheduled for May 11 through May 31 between 6 PM - 2:30 AM and vehicles are NOT permitted to park in the parking structure during these work hours. 

 

Updates

We understand the importance of keeping the community informed. Public Works and Engineering will provide updates throughout the project's duration.

 